September 13 - Preliminary Design Review (with mentors)
We are currently in the process of locating mentors from a variety of locations, including the local NAR chapter and regional universities.
September 18 - Changes to Preliminary Design Review completed
September 25 - Prototype design and preparation complete
October 4 - Final Design Summary
October 8 - October 18 - Fabrication of prototype
October 22-25 (Tentatively) - Start first round of testing for TARC rocket
Testing depends on the completion of the rocket prototype and weather.